MIL-HDBK-1003/1
(c) Adjacent areas to meat coolers and milk, butter, and egg rooms.
When automatic priming is through a device connected to the water system, provide that device equipped with a vacuum breaker."
SECTION 412.5 Add the following: "Refer to Appendix H for additional requirements for use on Navy projects."
Add "SECTION 501.9 Multiple Water Heaters. Provide hospitals, laundry buildings, subsistence buildings, bachelor officers' quarters with mess and enlisted men's barracks with mess with multiple water heaters and storage tanks. Provide other facilities with a single water heater and storage tank. Multiple units, however, may be justified by circumstances
such as (1) facility configuration, (2) space limitations, (3)
limited access to tank room, and (4) hot water requirements
necessitating an unusually high capacity heating and storage
unit. When two units are provided, each will have a capacity
equal to two thirds of the calculated load. When more than
two units are provided, their combined capacity will be equal
to the calculated load."
Add "SECTION 504.9 Vacuum Breaker. Provide a vacuum breaker on each copper-lined storage tank to prevent the creation, within the tank, of a vacuum which could cause loosening of the lining."
Add "SECTION 505.2 Insulation of Hot Water Piping. Insulate service hot water piping and storage to meet the more restrictive minimum requirements of the following:
(1) IPC.
(2) ASHRAE Standard 90.1."
Add "SECTION 505.3 Upgrade Insulation. The insulation requirements and maximum heat loss rates stated in this section are minimum design requirements. The designer is
encouraged to upgrade the quality of insulation if he can show
an improvement in the system performance, or that the
insulation is cost effective, or both."